According to SBM's business coverage, we have established strong installation engineer teams and divided them into several parts according to the businesses, including building aggregate team, ore processing team and industrial milling team. Each team consists of young, middle-aged, and old engineers, fully satisfying business requirement and fulfilling talent cultivation objective.

Summary : Concrete Jaw Crusher installation process There are various types of Concrete Jaw Crushers, but no matter which type is used, as long as it is a fixed Concrete Jaw Crusher, it needs to be installed first and then need to be debugged. …

Concrete Jaw Crusher installation process

There are various types of Concrete Jaw Crushers, but no matter which type is used, as long as it is a fixed Concrete Jaw Crusher, it needs to be installed first and then need to be debugged. The next step is the processing of materials. Here we introduce Is the installation process of the machine.

The installation of the Concrete Jaw Crusher is mainly installed on the foundation. The installation requirements are sturdy, which can ensure the smooth operation of the equipment. Professional tools are required during installation, and the staff is required to have certain structure, performance and principle of the Concrete Jaw Crusher. Understand the rigorous inspection before installation, the inspection process is to ensure the installation conditions and the equipment itself is complete, the installation process can be divided into several different parts, mainly as follows:

1, the installation of the base

The Concrete Jaw Crusher is a separate base. It is hung on the foundation of the good slurry. After leveling and irrigating the foundation, the anchor bolt holes and the pre-embedded anchor bolts are reserved. The exposed base surface is 120mm. After the concrete is solidified, the bottom is tightened. Foot bolts. After reaching the technical requirements, the two side columns are respectively hung on the base, and the column is fastened after being found;

2, the installation of the roller

After the base and the column are adjusted, the hopper is placed first, and then the roller is separately loaded into the bracket of the column to adjust it to meet the technical requirements. In addition, the Concrete Jaw Crusher has 8 lengths in the horizontal direction. Stud bolts used to control the horizontal movement caused by the large force of the roller during operation;

3. Installation of the transmission part

The drive of the Concrete Jaw Crusher is completed by the motor and the pulley passing the rollers before and after the drive. During the installation process, the coupling pulleys must meet the technical specifications;

4. Installation of hydraulic and lubrication stations

The hydraulic station is piped to the hydraulic cylinder block, and the hydraulic lubrication pipe follows the position of the hydraulic station valve table during the installation process—pipe-welding-removing pickling-blow-drying-recovery pipe-nitrogen-oil-washing-inspection-commissioning production, And in line with hydraulic, lubrication, pipeline construction process;

5. Inspection before commissioning

After the Concrete Jaw Crusher is installed, the Concrete Jaw Crusher should be thoroughly inspected, and all the scale inside and around the equipment should be removed and then tested.

Crusher Equipment

VSI5X Sand Maker
VSI5X Sand Maker
PEW Jaw Crusher
PEW Jaw Crusher
CI5X Impact Crusher
CI5X Impact Crusher
PFW Impact Crusher
PFW Impact Crusher
K Track-type Mobile Crusher
K Track-type Mobile Crusher
PF Impact Crusher
PF Impact Crusher

Auxiliary Facilities

Request A Quotation